Project Budget Calculations
We collect data for cost and revenue budgets from areas within Workday to create the project budget.
Source | Per-Period Calculations |
|---|---|
Time | Approved time blocks and all ad hoc project time transactions for the project:
|
Journal Lines | The sum of all journal lines that match these elements:
|
Resource Forecast | If there are no actual worker hours logged to the worker time block or the ad hoc project time transaction, Workday draws on the resource forecast and uses:
|
Resource Plan | Workday draws estimates from the resource plan and uses:
|
Contract Rate Sheet | Workday gathers actual hours logged to the project and uses the project billing rate from the rate sheet on the customer contract, taking into consideration any billing rate rules.
Workday converts the currency into the project currency, if applicable. Conversion rates come from the Currency Rates As of Date task based on the resource forecast or snapshot date. Workday determines the currency rate type from the Default Currency Rate Type field specified on the Edit Tenant Setup-System task. |
Revenue Recognition Installments | Workday calculates Fixed Fee - Installment plans by pulling in installments from the revenue recognition schedule. Actuals come from journal lines. |
Calculated Project Budget Line | Workday calculates Fixed Fee - Percent Complete (Hours) contracts using this source when:
|
The calculation details for the project budget line are available on the
From the related actions menu of a draft or approved project budget, select.
View Initial Calculation
report.
This report doesn't include manual changes to project budget lines.
Calculation Detail | Description |
|---|---|
Resource | Includes:
|
Role | Project worker, associated group, or unnamed resource role assignment on the resource plan line. |
Period | Inclusive date range for calculation. |
Hours | Total number of hours used in calculation. |
Ledger Account | Ledger account for actuals. |
Source | Draws from 1 of these origins:
|
Cost Rate | Cost rate derives at:
|
Cost Rate Currency | Cost rate currency derives at:
|
Cost Amount (Source Currency) | Multiplies the cost rate by hours using the source currency. |
Cost Amount (Budget Currency) | Multiplies the cost rate by hours using the budget currency. |
Cost Worktags | Worktags define:
If the same worktag type defines the project and the time cost, the project worktag overrides the configuration worktag. |
Billable Hours | The total number of billable hours used in calculation. For project budgets created from resource forecasts at the task level, billable hours include:
|
Days for Period | Calculates days from the contract rate sheet. |
Billing Rate | Draws the contract rate sheet from the first applicable transaction for the period. |
Billing Rate Currency | Draws from the contract rate sheet. |
Revenue Amount (Source Currency) | Uses the source currency, the billable hours, and the billing rate with considerations from the billing rate rules. |
Revenue Amount (Budget Currency) | Uses the budget currency, the billable hours, and the billing rate with considerations from the billing rate rules. |
Billing Rate Rules | The billing rate rule types applied to calculate the revenue amount. These rules are from the contract rate sheet. |
Project Inception to Date Hours | Workday calculates Fixed Fee - Percent Complete (Hours) revenue calculation methods as the total hours worked for matching budget lines from prior periods through the current period. |
Project Estimated Hours at Complete | Workday calculates Fixed Fee - Percent Complete (Hours) revenue calculation methods as the total hours worked by all project resources. |
Percent Complete by Hours | Workday calculates Fixed Fee - Percent Complete (Hours) revenue calculation methods as the Project Inception to Date Hours divided by the Project Estimated Hours At Complete . |
Contract Amount | The total contract amount for Fixed Fee - Percent Complete (Hours) revenue calculation methods. |
Total Recognizable Revenue | Workday calculates Fixed Fee - Percent Complete (Hours) revenue calculation methods as Percent Complete by Hours multiplied by Contract Amount . |
Previously Recognized Revenue Amount | Workday calculates Fixed Fee - Percent Complete (Hours) revenue calculation methods as matching budget lines (role, resource, and worktags from prior periods) in the Budget Currency . |
Calculated Allocation | Workday calculates Fixed Fee - Percent Complete (Hours) revenue calculation methods as the allocation of journal lines for the period to:
|
Total Plan Remaining | Workday calculates the total plan remaining based on an available approved baseline plan.
When an approved baseline plan isn't available, then the calculation is based on the last approved budget. If neither are available, then the calculation is based on your estimated budget. |