Reference: Project Budget Calculations
We collect data for cost and revenue budgets from
areas within Workday to create the project budget.
Source | Per-Period Calculations |
|---|---|
Time | Approved time blocks and all ad hoc project time transactions for the
project:
|
Journal Lines | The sum of all journal lines that match these elements:
|
Resource Forecast | If there are no actual worker hours logged to the worker time block or
the ad hoc project time transaction, Workday draws on the resource forecast
and uses:
|
Resource Plan | Workday draws estimates from the resource plan and uses:
|
Contract Rate Sheet | Workday gathers actual hours logged to the project and uses the project
billing rate from the rate sheet on the customer contract, taking into
consideration any billing rate rules. Workday converts the currency into
the project currency, if applicable. Conversion rates come from the
Currency Rates As of Date task based on the
resource forecast or snapshot date. Workday determines the currency rate
type from the Default Currency Rate Type field
specified on the Edit Tenant Setup-System
task. |
Revenue Recognition Installments | Workday calculates Fixed Fee - Installment plans
by pulling in installments from the revenue recognition schedule. Actuals
come from journal lines. |
Calculated Project Budget Line | Workday calculates Fixed Fee - Percent Complete
(Hours) contracts using this source when:
|
The calculation details for the project budget
line are available on the From the related actions menu of a draft or
approved project budget, select.
View Initial Calculation
report.This report doesn't include manual
changes to project budget lines.
Calculation Detail | Description |
|---|---|
Resource | Includes:
|
Role | Project worker, associated group, or unnamed resource role assignment
on the resource plan line. |
Period | Inclusive date range for calculation. |
Hours | Total number of hours used in calculation. |
Ledger Account | Ledger account for actuals. |
Source | Draws from 1 of these origins:
|
Cost Rate | Cost rate derives at:
|
Cost Rate Currency | Cost rate currency derives at:
|
Cost Amount (Source Currency) | Multiplies the cost rate by hours using the source currency. |
Cost Amount (Budget Currency) | Multiplies the cost rate by hours using the budget currency. |
Cost Worktags | Worktags define:
If the same worktag type defines the project and the time cost, the
project worktag overrides the configuration worktag. |
Billable Hours | The total number of billable hours used in calculation. For project
budgets created from resource forecasts at the task level, billable hours
include:
|
Days for Period | Calculates days from the contract rate sheet. |
Billing Rate | Draws the contract rate sheet from the first applicable transaction for
the period. |
Billing Rate Currency | Draws from the contract rate sheet. |
Revenue Amount (Source Currency) | Uses the source currency, the billable hours, and the billing rate with
considerations from the billing rate rules. |
Revenue Amount (Budget Currency) | Uses the budget currency, the billable hours, and the billing rate with
considerations from the billing rate rules. |
Billing Rate Rules | The billing rate rule types applied to calculate the revenue amount.
These rules are from the contract rate sheet. |
Project Inception to Date Hours | Workday calculates Fixed Fee - Percent Complete
(Hours) revenue calculation methods as the total hours
worked for matching budget lines from prior periods through the current
period. |
Project Estimated Hours at Complete | Workday calculates Fixed Fee - Percent Complete
(Hours) revenue calculation methods as the total hours
worked by all project resources. |
Percent Complete by Hours | Workday calculates Fixed Fee - Percent Complete
(Hours) revenue calculation methods as the Project
Inception to Date Hours divided by the Project Estimated Hours At
Complete . |
Contract Amount | The total contract amount for Fixed Fee - Percent Complete
(Hours) revenue calculation methods. |
Total Recognizable Revenue | Workday calculates Fixed Fee - Percent Complete
(Hours) revenue calculation methods as Percent Complete
by Hours multiplied by Contract Amount . |
Previously Recognized Revenue Amount | Workday calculates Fixed Fee - Percent Complete
(Hours) revenue calculation methods as matching budget lines
(role, resource, and worktags from prior periods) in the Budget
Currency . |
Calculated Allocation | Workday calculates Fixed Fee - Percent Complete
(Hours) revenue calculation methods as the allocation of
journal lines for the period to:
|
Total Plan Remaining | Workday calculates the total plan remaining based on an available
approved baseline plan. When an approved baseline plan isn't available,
then the calculation is based on the last approved budget. If neither
are available, then the calculation is based on your estimated
budget. |