Steps: Set Up Resource Forecasts
- Review setup considerations for resource forecasts.
- Create a project. See Create Projects.
- Set up resource plans. See Steps: Set Up Resource Plans.
You can:
- Use resource forecasts to estimate monthly, weekly, or daily estimated hours for the workers on your projects.
- On the Resource Forecaster, see whether workers are over, under, or fully allocated.
- Enable project workers to update their own resource forecasts and route changes to a manager for approval.
- Enter fractional or whole numbers for the forecast hours.
- Include both individual workers and unnamed resources in your forecasts.
Workday can generate these types of resource forecasts:
- Project-level forecasts based on the resource assignments in the resource plan.
- Task-level forecasts based on the assignments of the task resources in the project plan.
You can't delete the resource forecasts that you use to create project budgets or resource forecast snapshots.
The Resource Forecast report will be retired in a future release. Workday recommends that you use the Resource Forecaster for a more streamlined resource forecasting workflow.
- If necessary, set up the composite view of the project profile to include theResource ForecastandResource Forecasterreports on theResourcestab of the project profile.
- Access theConfigure Profile Grouptask.
- From theProfile Groupprompt, select theResources for Project Composite View Profilegroup.
- Add theResource ForecastandResource Forecasterreports, as needed, to the profile group.
- Edit Domain Security Policies.Edit these domains and security policies:
- Manage: Project Resource Forecastdomain in the Projects functional area. Project and resource managers need this security to create resource forecasts.
- (Optional)Self-Service: Resource Forecastdomain in the Projects functional area. Project workers need this security to access self-service data and tasks.
- (Optional)WorksheetsandDrivedomains in the System functional area. Project and resource managers need this security to edit resource forecasts using a worksheet.
- Edit the security policies for these business processes:
- Project Resource Plan Linein the Project Tracking functional area. Project and resource managers need this security to create resource plans.
- (Optional)Update My Resource Forecastin the Projects functional area. Project workers need this security to update their resource forecasts.
- (Optional) Edit Business Processes.Edit theUpdate My Resource Forecastbusiness process in the Projects functional area to enable:
- Workers to update their own resource forecasts.
- Managers to approve the forecast change initiated by the workers.
- (Optional) To enable users to edit resource forecasts with worksheets:
- Set Up Worksheets and enable worksheets for your tenant.
- Access theEdit Tenant Setup - Financialstask. In theProjectssection, select theEnable Worksheets for Resource Forecastcheck box.
Security:Set Up: Tenant Setup - Financialsdomain in the System functional area. - Create a resource plan for the project, and then add workers to the resource plan lines.
- (Optional) Enable resource forecasts to display detailed task information.
- Access theCreate Resource Forecast for Projecttask (to use the Resource Forecast report) or theCreate Resource Forecast for Project via Resource Forecastertask (to use the Resource Forecaster report).For theForecast Level View, when you select:
- Project, Workday generates a project-level forecast that contains the worker and their forecasted hours.
- Project Plan Task, Workday generates a detailed forecast that includes the worker, their project tasks, and their forecasted hours.
Security:Manage: Project Resource Forecastdomain in the Projects functional area.
Workday creates the resource forecast and displays a forecast line for each worker that includes the:
- Task, on the Resource Forecast report only. (Displays only if you created the forecast from the project plan task.)
- Total forecasted hours.
- Estimate at Completion (EAC). EAC includes all the hours logged and approved for the project. It also includes the future hours the worker expects to complete.
- Estimate to Completion (ETC). ETC includes the future hours the worker expects to complete.
- Forecast hours.
On the Resource Forecaster, Workday also displays an overlay of visual indicators showing whether workers are under, over, or fully allocated. You can toggle the indicators on or off using the gear button on the top-right of the grid, and you can hover or drill down on them to see a detailed view of the calculation.
Workday calculates the initial forecast hours based on the:
- Start and end dates.
- Percent allocation or estimated hours.
Create a project budget using the resource forecast.
Project workers can access the
Update My Resource Forecast
task to modify their own forecasts in these upcoming time periods:
- Current week + next 3 weeks for weekly forecasts.
- Today + next 9 days for daily forecasts.