Create Project Standard Cost Rate Sheets
- (Optional) Create Project Cost Rate Rules.
- Security:Set Up: Projectdomain in the Projects functional area.
Create project standard cost rate sheets to cost labor without accessing worker sensitive information. Configure standard cost rates for:
- Individual workers by name.
- Workers based on worker attributes.
- Workers or unnamed resources based on project roles.
You can override standard cost rates and currency on the project resource plan line.
- Access theCreate Project Standard Cost Rate Sheettask.
- As you complete the header, consider:
Option Description CurrencyDetermines the currency for worker costing. This currency can differ from the company currency.CompanyYou can create only 1 rate sheet per company. You can assign multiple companies to a rate sheet.Workday determines the cost rate sheet to use for:- Workers using the company from the worker primary position.
- Unnamed resources using the project company.
Default Hourly RateThe hourly rate populates the cost rate when either:- The worker doesn't meet any criteria.
- The project role doesn't define an unnamed resource.
Effective DateYou can post-date the effective date when you create or edit a standard cost rate sheet. Workday calculates and persists time entry costs upon time entry approval.The standard cost amount for approved project time entries doesn't change when:- The standard cost rate sheet doesn't change.
- The override to a cost rate on the resource plan line doesn't change.
Use theHistorytab to view effective date changes to the standard cost rate sheet. From the related actions menu of the standard cost rate sheet, select to view change activity.InactiveRetires the rate sheet permanently. Selecting this check box isn't reversible.Order of ExecutionDetermines the order of processing for the rate sheet tabs.If a worker qualifies for more than 1 rule, Workday applies the rate for the first rule that the worker qualifies for. TheOrder of Executionoption doesn't apply to unnamed resources. - As you complete the rate sheet tabs, consider:
Option Description Project Rate RuleDefines a group of workers based on a set of attributes, such as worker location, job profile, or company.WorkerConfigure a rate for a worker included in your list of companies for this rate sheet.Project RoleThe project role for a worker or unnamed resource.When a worker replaces the unnamed resource, Workday uses theOrder of Executionto determine the cost rate with the:- Project cost rate rule.
- Worker.
- Project role associated with the worker.
Standard cost rates are now available for:
- Capturing actual labor costs.
- Forecasting and budgeting project labor costs.
Configure your project advanced labor costing.
To view the workers in your resource plan, go to the project profile and select .
View Resource Rates
to view and compare project resource cost rates including:
- Fully burdened cost rate definition.
- Standard cost rate.
- Standard cost rate override.
If you make changes to a cost rate sheet and want to recalculate labor costs for approved time blocks and ad hoc project time transactions, you can access the
Recalculate Project Labor Costs
task.