Example: Calculate Nevada Rolling Overtime

Example: Calculate Nevada Rolling Overtime

This example illustrates how to create standard overtime calculations to comply with Nevada overtime regulations.
Nevada law requires companies to pay certain groups of workers overtime when they work more than 8 hours in a 24-hour period. You need to create a calculation that tags the appropriate hours as overtime.
  • Create a Time Calculation Group named Nevada Daily OT. See Create Time Calculation Groups.
  • Security:
    Set Up: Time Calculations
    domain in the Time Tracking Calculations functional area.
  1. Access the
    Create Time Calculation
    task.
  2. In the
    Name
    field, enter
    Nevada Rolling Overtime
    .
  3. From
    Calculation Type
    prompt, select
    Standard Overtime Calculation
    .
  4. Click
    OK
    .
  5. In the
    General Options
    tab, specify the
    Criteria
    .
    Field
    Value
    Period
    Rolling 24 Hours
    This setting disables the
    Include Scheduled Hours
    check box in the
    Advanced
    section.
    Rolling 24 Hour Period Begins
    Start of Day
    Replace Hours Greater than (value)
    8
    Workday calculates any hours greater than
    8
    as overtime.
    Time Calculation Tags
    Regular
    To include
    Hours Only
    time entries or time off in the overtime calculation, a 24-hour period must begin on that day.
  6. Specify the
    Results
    .
    Field
    Value
    Add Tags
    Overtime
    Remove Tags
    Regular
  7. In the
    Groups
    tab, add a row to the grid with these values:
    Field
    Value
    Time Calculation Group
    Nevada Daily OT
    Effective Date
    Current Snapshot
  8. Click
    OK
    .
  9. Access the
    Maintain Time Calculation Priorities
    task to assign this calculation priority 200.
  10. Click
    OK