Create Minimum Rest Calculations
- Create predictive scheduling configurations.
- Create a time calculation tag to use in minimum rest calculations.
- Security:Set Up: Time Calculationsdomain in the Time Tracking Calculations functional area.
A minimum rest calculation tags time blocks worked during a specified rest period. You can use minimum rest calculations to handle laws that require you to pay a premium if workers lack sufficient rest time between their shifts.
Minimum rest calculations don't account for time off blocks. Example: A worker is scheduled for a 12:00-8:00 PM shift. They work from 12:00-5:00 PM but then take 5:00-8:00 PM as sick time. The minimum rest calculation starts counting hours after the worker's 5:00 PM check-out.
- Access theCreate Time Calculationtask.
- ForCalculation Type, selectMinimum Rest Calculation.
- As you complete theCriteriasection, consider:
Option Description Predictive Scheduling ConfigurationSelect an existing predictive scheduling configuration or create a new one.After you select a configuration, Workday displays theAllowed Out TypesandMinimum Rest Hours After Last Outfields. Workday generates these fields from the predictive scheduling configuration, and you can only edit them on theEdit Predictive Scheduling Configurationtask.Minimum Rest Grace Period after Last OutDefine a grace period that begins after a worker's out. During the grace period, Workday won’t apply the minimum rest time calculation tag to time blocks.You can use the grace period to ensure that workers who check out for a short break don't qualify for the minimum rest premium.Example: You set a grace period of 2 hours. A worker checks out of work for a 1-hour break using the Out type you defined on the predictive scheduling configuration. After the break, the worker checks back in. Workday doesn't tag these time blocks with the minimum rest calculation tag because the worker's 1-hour break was within the 2-hour grace period. - In theResultssection, select the time calculation tags to add to or remove from the eligible time blocks.
- In theAdvancedsection, in theDo Not Modifyfield, select time calculation tags that you don't want Workday to modify.
- In theGroupstab, add time calculation group snapshots with the appropriate effective dates to specify which workers are eligible for the calculation.
Workers must take a 1 hour meal break. To tag time worked during meal breaks.
- Specify theMinimum Rest Period SettingsFieldValueAllowed Out TypesMealMinimum Rest Hours after Last Out (up to 48)1
- Define theResults.FieldValueAdd TagsMissed Meal
When a worker checks out at 11:00 with a reason of meal and checks back in at 11:30, Workday tags 11:30 to 12:00 with the
Missed Meal
tag. You can then report on the missed meal time or use the tag in time calculations to properly compensate the worker.Assign time calculation priorities.