Create Override Rate Calculations
- Security:Set Up: Time Calculationsdomain in the Time Tracking Calculations functional area.
Create calculations to assign override rates to workers' time blocks based on the details of the work they're doing. Example: You might pay workers a different rate when they work for a particular cost center. You can define multiple override rates in 1 calculation, assigning a rate to each combination of worktag values.
If you manually enter an override rate on a time block, that rate also overrides any override rate calculations that apply to the time block.
- Access theCreate Time Calculationtask.
- From theCalculation Typeprompt, selectOverride Rate Calculation.
- Select 1 or moreWorktags.The worktags you select determine the worktag detail combinations to which you can assign override rates.
- (Optional) Select aStart DateandEnd Dateto define a time period for the calculation to be in effect.The calculation is in effect for the time blocks reported for the time period. The time block date can be different from the date the time block is actually reported. Example: If the calculation is in effect starting on 2014-01-01, Workday includes a time block reported on 2013-12-31 for 2014-01-01 in the calculation but doesn't include a time block reported on 2014-01-01 for 2013-12-31.
- (Optional) SelectTime Calculation Tagsto further identify the time blocks to which you want to apply the override rates.
- Add a row in theRate Assignmentstable for each rate assignment that you want to define.
- Select a worktag value for each worktag.
- Enter anOverride Ratefor the worktag value or combination of worktag values.
- (Optional) Select aCurrencyfor the override rate.When you don't specify a currency, Workday Payroll uses the worker's default currency when referencing the override rate.
- In theGroupstab, add time calculation group snapshots with the appropriate effective dates to specify which workers are eligible for the calculation.
When workers enter time blocks that match the worktag type and time calculation tag conditions that you specified, Workday applies the appropriate override rate to the time blocks.
Assign time calculation priorities.