Setup Considerations: Project Budgets
You can use this topic to help make decisions when planning your configuration and use of project budgets. It explains:
- Why to set it up.
- How it fits into the rest of Workday.
- Downstream impacts and cross-product interactions.
- Security requirements and business process configurations.
- Questions and limitations to consider before implementation.
Refer to detailed task instructions for full configuration details.
What It Is
Project Budgets is the primary financial component within Projects. It enables you to analyze:
- Budget versus actuals.
- Cost versus revenue.
- Labor versus nonlabor.
- Primary variance contributors by various dimensions like ledger account, spend or revenue category, and supplier.
Business Benefits
Project budgets support:
- Analysis of project budget versus actuals across your organization.
- Automated labor cost calculations based on standard cost rates and forecasted hours.
- Automated revenue calculations based on contract rates, fixed fee installments, or fixed fee percent complete (hours).
- Worktag dimensions.
Use Cases
With project budgets, you can:
- Create high-level project duration budgets or more detailed monthly budgets.
- Create custom reports to understand your project revenue and costs.
- Develop flexible project budgets at different levels of granularity.
- Use Worksheets to update and maintain project budgets.
- View live data on project progress, time, and spend, as well as budgets and forecasts.
Questions to Consider
Questions | Considerations |
|---|---|
What project budget types do you need to manage? | You can create budgets to manage your cost projects, revenue projects, or both. Project budgets are available for:
You can:
|
What configuration level do you need to manage your project budgets? | You can configure your project budget at the project hierarchy level, the tenant level, or both.
Project hierarchy configurations take precedence over tenant configurations. |
Will you create your budget using prior actuals? | For cost budgets that you want to include actuals in, use this configuration to identify:
|
What dimensions do you want to track? | Create a plan structure and include the relevant dimensions.
You can make these dimensions required or optional. Each budget line must include required dimensions. |
What plan line attributes do you want to track? | By default, Workday classifies the plan lines for project budgets as cost or revenue.
You can also configure Workday to classify the plan lines for project budgets as labor or nonlabor. You can use the plan line attributes in custom reports to understand the financial health of your project. |
What resource forecast level do your project budgets have? | Workday generates resource forecasts at the:
|
Recommendations
When maintaining multiple budget periods at once, use Worksheets rather than updating each period individually.
Maintain at least 2 calculation types. These calculations types are:
- Baseline, which shouldn't include actuals.
- Forecast, which should include actuals.
Requirements
To ensure that Workday calculates Project Budgets accurately, you should:
- Understand projects.
- Understand project resource plans if generating your budget from your resource forecast or resource plan.
- For managing your project labor costs, create your standard cost rate sheet.
- For revenue budgets, define your project billing dependencies in Workday.
- For setting up budget check options, understand budgetary control functionality.
Limitations
Workday doesn't:
- Include committed costs, such as purchase orders in project budgets. You can manually add these transactions as budget line items.
- Support fully burdened costing, or percent complete by cost.
- Support the creation of workbooks from project plan budgets with more than 500 periods or more than 10 years in the future.
- Support using theSchedule Project Budget Mass Updatetask to update more than 5,000 plans.
Tenant Setup
No impact.
Security
Domain | Considerations |
|---|---|
Set Up: Project Hierarchy in the Projects functional area | Can configure and update project budgets on the project hierarchy. |
Set Up: Project Budget in the Projects functional area | Can configure and update project budgets on the tenant. |
Manage: Project Budget in the Projects functional area | Can manage and view budget information. |
Manage: Project Resource Forecast in the Projects functional area | Can manage and view resource forecast information. |
Access Plan Type (segmented) in the Budgets and Projects functional areas | Can control access to project budgets. |
Workday uses multiple roles to configure project budgets. However, since several steps in the process are one-time only, project budgets require minimal maintenance.
Role | Considerations |
|---|---|
Security Administrator | Configures security. Adds project administrators to the proper security groups. |
Budget Administrator | Adds Project as an entry type. |
Project Administrator | Configures project budgets on the:
Defines standard cost rates for:
|
Project Hierarchy Administrator | Defines the project budget by configuring:
|
Project Manager | Creates and updates project budgets.
Creates plans as outlined by the plan structure and project hierarchy configurations. Assigns plans as baselines or forecasts to compare variances across projects in the hierarchy or tenant. Creates a revised budget for changes to:
Manages budgetary control options. Tracks spend and revenue. Analyzes:
|
Contract Administrator for Revenue Budgets | Defines the billing rate that Workday uses to calculate the revenue budget. |
Business Processes
Business Processes | Considerations |
|---|---|
Assign Plan as Baseline Event
| Can designate the calculation type as a baseline budget. |
Budget Amendment Event
| Can submit amendments for budget templates requiring approval or amendment. |
Plan Event
| Can create a budget when the budget template requires approval or amendments. |
Reporting
Reports | Considerations |
|---|---|
Project Budgetary Balance With Labor Cost | You can compare the budget for a project to the actual cost. This report doesn't apply to duration budgets. |
Project Hierarchy Baseline vs. Forecast | Enables organization level reporting on baseline versus forecast at your project hierarchy or tenant level. You can customize this report to include the dimensions and variance thresholds appropriate for your organization. |
You can use these report data sources to create custom reports:
- All Budget Amendments
- Budget Amendments by Organization
- Project Budget Calculation Details
Integrations
You can use these web services to upload your project budgets:
- Import Budget: Add project budget lines without creating it manually in Workday. Use after you've created a budget.
- Import Budget Amendment: Amend multiple project budgets at once.
- Put Budget Template: Create your project budget without creating it manually in Workday.
- Put Project Budget Template: Create a template that you can use to create a project budget from within the UI.
Connections and Touchpoints
Project Budgets interacts with:
- Financial accounting.
- Time tracking.
Workday offers a Touchpoints Kit with resources to help you understand configuration relationships in your tenant. Learn more about the Workday Touchpoints Kit on Workday Community.