Example: Use Unnamed Resources in Projects
This example explains how to use unnamed resources in your projects.
You need to define the resources and scope the work effort for a 1-month project before you
can fully staff it. You add unnamed resources allocated at 100% as placeholders on
the resource plan, resource forecast, and task resources for the project. Once
complete, you then review the:
- Estimated work effort for each project worker.
- Task assignments for each project worker.
Create a project hierarchy.
Configure these business processes and security policies:
- Create Projectin the Project Tracking functional area.
- Edit Projectin the Project Tracking functional area.
- Project Resource Plan Linein the Project Tracking functional area.
- Request Workerin the Projects functional area.
Security: These domains in the Project Tracking functional area:
- Manage: Project Details
- Manage: Project Plan
- Set Up: Project Details
- Access theCreate Projecttask.
- Create a project without selecting any templates.
- Enter today as the Start Date.
- Access theCreate Project Plantask.
- Create a project plan for your project without selecting a template.
- Add 1 phase and 1 task to your plan.
- Access theCreate Resource Plan for Projecttask.
- Create a resource plan for your project without selecting a template.
- Enter these values on theResource Plan Line:
OptionValueProject RoleConsultantStart DateTodayEnd DateA date 1 month in the future.Allocation TypeAssign a Worker% Allocation100Add Unnamed Resources3Workday adds your unnamed resources to the resource plan line using the role name appended with an incremental number. Example: Consultant-1, Consultant-2, Consultant-3. - Access theEdit Task Resourcesreport.
- Select your project.
- Add 3 rows to theTask Resourcesgrid.
- As you complete each row, select these values:
OptionValueProject ResourcesAn unnamed resource.Example:Consultant-1Resource Plan LineConsultantResource Start DateTodayResource End DateA date 1 month in the future.% Allocation100You see a grid of your unnamed resources and their task assignments for the project. - Access theCreate Resource Forecast for Projecttask.
- Select your project.
- As you complete the task, enter these values:
OptionValueForecast Level ViewProjectForecast Frequency ViewWeekForecast SourcePercent AllocationForecast HoursWhole NumbersYou see the work estimate for your unnamed resources on the resource forecast. - Access theView Projectreport and select your project.To review and verify your unnamed resources:
- Click theResourcesprofile group.
- Click theProject Resourcestab. You see your unnamed resources in the grid.
- Click theResource Plantab. You see your unnamed resources in theWorkerssection on the resource plan line.
- Click theResource Forecasttab. You see your unnamed resources and their estimated hours in the grid.
- Click theProject Planprofile group.
- Click theTask Resourcestab. You see your unnamed resources and their assigned project tasks in the grid.
When you’re ready to assign specific workers to your project, use a Find Worker report to replace
the unnamed resources with project workers:
- Navigate to the resource plan.
- Click theFind Workersbutton.
- Assign a worker to the project.
Workday replaces 1 of the unnamed resources with the new worker, and then automatically
updates the project resources, resource forecast, and task resources with your new
worker assignment.