Configure Task Resources
- Create a project.
- Create a resource plan.
- Create project tasks.
- Create a project plan.
- Security:Manage: Project Task Resourcesdomain in the Projects functional area.
By configuring task resources, you can add these assignments to specific project plan tasks:
- Individual project workers.
- Unnamed resources.
- Worker groups.
These task resource assignments enable:
- Project workers to log their time to their specific task assignments with Time Tracking and ad hoc project time transactions.
- Project managers to create detailed resource forecasts.
- Project managers to create detailed project budgets.
- Access the project.
- SelectProject Plan.
- Select 1 of these tabs:
- Project Planner.
- Task Resources.
- (Optional) ClickEdit in Gridto update the task resources in a table format.Available on theTask Resourcestab only.
- Select or expand a project plan task and enter the assignment details.As you complete the task, consider:
Option Description Project ResourcesSelect specific workers or unnamed resources who are available for assignment from the resource plan line.Workers that you assign as task resources can enter time to a project plan task in Time Tracking or through ad hoc project time transactions.Workers on the resource plan can view and log time to a task without task resources on both billable and nonbillable projects.To modify this field on the Project Planner, select a task resource line and click the pencil icon.Resource Plan LineIdentifies the project role on the resource plan line. Workday populates this field based on the worker.This field displays even when the role is an association or not yet hired.To modify this field on the Project Planner, select a task resource line and click the pencil icon.Resource Start DateorStart DateResource End DateorEnd DateEnter a start date that's on or before the end date.Workday doesn't require or enforce date relationships across:- Projects.
- Project plan tasks.
- Resource plan lines.
- Task resources.
Example: You can assign a worker as a task resource with dates outside their resource plan line.% AllocationAvailable on theTask Resourcestab only.Percentages automatically populate from the resource plan line when available. Or, you can enter a new value.Workday supports whole numbers that are greater than or equal to zero and percentages over 100.Estimated HoursEnter the number of hours you estimate the task takes. You can enter positive numbers up to 2 decimal points.MemoEnter details to track historical changes to:- Estimated hours.
- Start and end dates.
- Any other task resource updates.
The memo you enter here follows the worker to display on theEdit Task Assignmentsubtask for theFind Worker Availabilityreport. - (Optional) ClickMass Updateto set or move the start and end dates for multiple resources at once.
- Synchronize the resource plan and task resource dates from the resource plan on the project.
- Identify conflicts in contract billing rates with theTask Resource Auditreport on the project.
- Set up resource forecasts.