Create Templates for Award Task Lists
- Create:
- Award task types.
- Award schedules.
- Security:Set Up: Grants Managementdomain in the Grants Management functional area.
Award task list templates enable you to create lists of award tasks to meet the
reporting requirements of a sponsor, award type, or purpose code. You can:
- Schedule task milestones for particular dates and posting intervals.
- Enable task milestones to reoccur during the life of the award.
- Use templates during task creation to generate tasks in multiple task lists.
- Access theCreate Award Task List Templatetask.
- As you complete theValid forsection, consider:
Option Description Award Posting Interval GroupTo use this template on awards that have a specific posting interval group, select that posting interval group. To use this template on multiple awards with different posting interval groups, don't select any posting interval group. When you create an award task list from this template, Workday generates the reoccurring tasks across the posting interval you select.Closeout TemplateSelect this check box to dedicate the template to only closeout tasks.Workday recommends that you create separate templates for closeout and noncloseout tasks, and use both templates to create your award task lists. - (Optional) In theAward Task Templatesection, add the award tasks required for the sponsor, award type, or purpose code.As you complete each task, consider:
Option Description Task TypeSelect from the list of award task types you created when you set up the award tasks.Closeout TaskYou can define a task as a closeout task in the award task type.RoleSelect the roles that can complete the task in the awards.Due Date, Start Date, End DateSelect a date for the task relative to the anchoring period.To ensure that your report is complete before it's due, always set the due date to be later than the end date.Example:To generate a report that:- Starts 10 days before the beginning of the award schedule.
- Ends on the last day of the award schedule.
- Is due 1 month after the award schedule ends.
- Due Date: 1 month after the end of the award schedule period.
- Start Date: 10 days before the beginning of the award schedule period.
- End Date: On the day of the end of the award schedule period.
When you create an award task list from this template, Workday copies all the tasks
from the template into the award task list, and calculates the actual dates. You can
delete tasks you don't need and make other edits to suit your reporting needs.
When you specify relative dates, you enable auto-generation of actual dates for all
relevant years. If a five-year award requires an annual progress report, Workday
generates 5 tasks on the award task list from the first task you enter on the
template.