Steps: Link Contracts
Add a supplier to the contract.
You can create relationship links between contracts with a supplier or link contracts to projects.
- Access theRelated Contractstab from a contract.Create a parent or child relationship link to a new or existing contract. You can only have 1 parent per contract.You can only link contracts if they have the same supplier.
- Access theRelated Projectstab from a contract.If you create a new project from this tab, it's automatically linked to the contract.
Access the
Relationship Tree
from the Related Contracts
tab of a contract to see how contracts are linked.