Concept: Dates in Payroll Off-Cycle Payment EIB Spreadsheets
When uploading multiple off-cycle payments through an EIB spreadsheet, you need to indicate the period to which the payment applies.
These examples illustrate how to complete the EIB spreadsheet for the
Import Payroll Off-Cycle Payment
web service for a period with multiple subperiods.
Workday recommends that you use the
Import Payroll Off-Cycle Payment
web service, because it's optimized for bulk import. These examples also apply to EIBs based on the Put Payroll Off-cycle Payment
web service.- Example: On-Demand Additional Payments with Subperiods
- On January 21, Julia's work state changes, creating 2 subperiods:
- January 1 - January 20.
- January 21 - January 31.
You want to upload a bonus for Julia, but you need to prorate the bonus payment for each period.In the EIB spreadsheet, enter a separate payment with:- A differentPayment IDfor each subperiod.
- APeriod Datethat corresponds to each subperiod.
Header KeyPayment IDPeriod DateResult TypeReplacementOff-Cycle Input Data -Row IDEarningAmount160002021-01-20OnDemandPaymentN1Bonus2000260012021-01-31OnDemandPaymentN1Bonus1000 - Example: On-Demand Replacement Payments with Subperiods (AUS, CAN, FRA, UK, USA)
- On January 21, Robert's primary job changes, creating 2 subperiods:
- January 1 - January 20.
- January 21 - January 31.
You want to upload a replacement payment for the work performed in the first subperiod.Add this row to the EIB spreadsheet:Header KeyPayment IDPeriod DateResult TypeReplacementOff-Cycle Input Data -Row IDEarningAmountReference Date170002021-01-31OnDemandPaymentY1Bonus20002021-01-20Workday uses theReference Dateto determine the applicable reference worktags and subperiod. TheReference Datebecomes view-only after Workday calculates the payment. To change the reference date, cancel the payment using theRun Pay Canceltask, and re-enter the date.Only use theReference Datecolumn for on-demand replacement payments.
- Example: Next Period On-Demand Replacement Payments (AUS, CAN, FRA, UK, USA)
- Ramona is terminated today, March 4. The monthly pay period for February is stillIn Progress. You need to pay her today for the days she worked in March.Add this row to the EIB spreadsheet:Header KeyPayment IDPeriod DateResult TypeReplacementOff-Cycle Input Data -Row IDEarningAmount171002021-03-04OnDemandPaymentY1Salary900Enter aPeriod Datein the period immediately after the currentIn Progressperiod.You can upload an on-demand replacement payment for Ramona's February pay in the same spreadsheet. You'll need to calculate and complete the February pay result before you calculate and complete the March result.
- Example: On-Demand Payments for Inactive Workers
- You want to upload an on-demand additional payment for Louis, who was terminated on March 25th. The payment covers the pay period from March 1 to March 31.Add this row to the EIB spreadsheet:Header KeyPayment IDPeriod DateResult TypeReplacementOff-Cycle Input Data -Row IDEarningAmount17500OnDemandPaymentN1Bonus1500Ensure that thePeriod Datecorresponds to the worker's termination date, or another date in which the worker was active.