Concept: Day Breakers
The day breaker on a worker's work schedule calendar defines the start time of a worker's
workday and work week. The day breaker setting also specifies how Workday should assign
dates to calculated time blocks.
Workday assigns the same calculated date to every time block on a day, whether or not the
time blocks cross calendar days. This approach has an impact on calculations such as
standard daily and weekly overtime calculations. The day breaker ensures that a
calculated date represents an exact 24-hour period. As a result, daily overtime
calculations apply over a 24-hour period regardless of the worker's shift or actual work
times. Similarly, weekly overtime calculations apply over a 168-hour period, regardless
of the worker's shift or actual work times.
When a worker clicks
OK
during time entry, Workday splits time
blocks according to the day breaker and assigns calculated dates to calculated time
blocks. The worker's reported time blocks remain on the time entry calendar as
originally reported, but Workday uses the calculated time blocks to run calculations.
You can view calculated time blocks on the Calculated
tab of
reported time blocks.Calculated Time Block Date
When a reported time block crosses the day breaker, the
Day Breaker
Divides
setting on the work schedule calendar determines which date
Workday assigns to the calculated time block. Workday splits the reported time block
into 2 calculated time blocks. Workday then assigns the appropriate date to each
block based on whether you select Current day from previous day
or Current
day from next day
.- Example: Current Day from Previous Day
- The day breaker is 3:00 PM and theDay Breaker Dividessetting isCurrent day from previous day.Workday assigns:
- The previous calendar date to time blocks before the day breaker.
- The reported calendar date to time blocks after the day breaker.
Reported Time BlocksCalculated Time Blocks6:00 AM - 3:00 PM, February 236:00 AM - 3:00 PM, February 2211:00 AM - 5:00 PM, February 2311:00 AM - 3:00 PM, February 223:00 PM - 5:00 PM, February 233:00 PM - 11:00 PM, February 233:00 PM - 11:00 PM, February 23 - Example: Current Day from Next Day
- The day breaker is 3:00 PM and theDay Breaker Dividessetting isCurrent day from next day.Workday assigns:
- The reported calendar date to time blocks before the day breaker.
- The next calendar date to time blocks after the day breaker.
Reported TimeCalculated Time Blocks6:00 AM - 3:00 PM, February 236:00 AM - 3:00 PM, February 2311:00 AM - 5:00 PM, February 2311:00 AM - 3:00 PM, February 233:00 PM - 5:00 PM, February 243:00 PM - 11:00 PM, February 233:00 PM - 11:00 PM, February 24
Day Breaker Changes
Workday evaluates day breakers on a daily basis when calculating time so that you can change a
worker's day breaker in the middle of a week.
Example: You assign a worker to a new work schedule with a different day breaker. Workday
calculates the first part of the week (before the change) according to the original
day breaker. Workday calculates the second part of the week according to the new day
breaker.
If a worker enters time between the end of 1 day breaker and the start of the next day
breaker, Workday calculates their time according to a midnight day breaker. Workday
then gives their time block a calculated date of the calendar date.