Configure Scramble Plans for Compensation
- Review Concept: Data Scrambling.
- Security:Scrambler Administrationdomain in the System functional area.
You can scramble or remove compensation data in Implementation tenants for training and testing purposes, or to cloak sensitive information.
Scrambling permanently changes or removes data. Scramble data in Implementation tenants only.
When you submit more than 1 scramble field at a time, Workday removes data before scrambling. Example: When you configure both the
Removal of Compensation Assignments and Payments
and Allowance Plans
scramble fields, Workday removes plan assignments, leaving no allowance plan assignments to scramble.Workday doesn't scramble plan defaults that equal zero.
- Access theCreate Data Scramble Plantask.
- As you complete theCompensationsection, consider these scramble fields and scramble methods:
Option Description Allowance PlansBonus PlansCommission PlansMerit PlansOne-Time Payment PlansStock PlansSelect:- Any option beginning withInput Value, Increment Profiles, and Update.For each plan type, select a scramble method and enter values forAmount,Percent, or theNumber of UnitsandPer Unit Amount.Workday scrambles:
- Amount-based plan defaults, assignments, and payments to the value specified forAmount. For commission plans, Workday scrambles both the amount and the draw amount.
- Percent-based plan defaults and assignments to the value specified forPercent.
- Unit-based plan defaults and assignments to the values specified forNumber of UnitsandPer Unit Amount.
- Set to Plan or Plan Profile DefaultWorkday:
- Overrides compensation assignments and payments with individual targets.
- Sets the plan or plan profile default to plan assignments, payments, and any grants. For commission plans, Workday scrambles both the amount and the draw amount.
Workday assigns the new scrambled default or profile default value to those employees that don't have individual targets on their plan, depending on their eligibility.Compensation ElementsCompensation Grades, Grade Profiles, and Grade HierarchiesCompensation PackagesCompensation PlansFor both methods, Workday generates a generic name for each object and appends a dash and the next number in sequence. Example:General Salary Planrenamed toSalary Plan - 1.Select:- Scramble to Number Sequence (Names and Descriptions)
- Scramble to Number Sequence (Names, Descriptions, and Reference IDs)Workday also renames all object Reference IDs to match the name of the scrambled object.
Compensation Pay RangesSelect:Input Percentage Varianceand enter the percentages to decrease the minimum and increase the maximum.Workday:- Selects random values according to your input percentage variance settings for the minimum and the maximum.
- Recalculates the segments in between evenly.
Workday recalculates segments the same as theCalculate Segmentscheck box on theCreate Compensation Gradetask.Removal of Compensation Assignments and PaymentsRemove all guidelines, plan assignments, and payments. Or, remove selected plan assignments and payments, but not guidelines.- Remove All Guidelines, Plan Assignments, and Payments
- Remove Selected Plan Assignments and Payments
Removal of Compensation Review DataWorkday removes all compensation review:- Plan assignments.
- Employee or organization-specific award data.
- Scorecards and profiles.
- Organization / budget pool contributions.
- Statements.
Salary and Hourly PlansSelect:- Input Percentage Threshold for Salary and Hourly AssignmentsWorkday scrambles all salary and hourly plan assignment values to a random value between the minimum and your specified threshold percentage of the total base pay range.Example: The total base pay range for an hourly plan is 10 through 20. You want to scramble that to a random point between the minimum (10) and 50% of the range (15), so you enter 50 for the threshold percentage. Workday scrambles the hourly plan assignment to 12, which is a random point between the minimum of 10 and the threshold percentage of 15.
- Input Value and Update AssignmentsEnter values for hourly plan defaults, hourly assignments, and salary assignments.Workday:
- Sets hourly plan defaults and assignments to the value you specify forHourly Assignments.