Skip to main content
Administrator Guide
Last Updated: 2024-09-20
Concept: Calculating Leave Taken

Concept: Calculating Leave Taken

To determine the number of days to count as taken for a leave request, Workday:
  • Uses the
    Days to Include
    option on the
    Balance/Leave Taken
    tab of the
    Create Leave Type
    task.
  • Calculates the hours for each day taken, if the leave type is hourly.
  • Takes the total scheduled hours for a worker across all eligible positions and divides it by the number of days in the week.
  • Prorates leave units if you select
    Prorate by Leave Percentage
    for the leave type and workers enter a leave percentage on the leave request.
Options that reference work days require a holiday calendar and a work schedule calendar.
This table explains how Workday determines days and hours taken for each option:
Days to Include
Days Counted as Taken
Hours Counted for Each Day Taken
Example
All Days
Every day
Scheduled weekly hours divided by 7.
Jane is scheduled to work 35 hours a week. Each day of leave is equal to 35 ÷ 7, or 5 hours.
Weekdays (Mon - Fri)
Monday through Friday only.
Scheduled weekly hours divided by 5. Workday ignores weekends.
Dawn is scheduled to work 35 hours each week. Each day of leave on a weekday equals 35 ÷ 5, or 7 hours. Workday doesn’t count hours for Saturday or Sunday.
Workdays (Non-Holiday)
Work days the worker is scheduled to work, excluding work days that are holidays.
Scheduled hours for the leave date, as determined by the work schedule and holiday schedule. Workday doesn’t include hours during holidays, even if the worker is scheduled to work that day.
Hahn is scheduled to work:
  • 9 hours on Monday.
  • 8 hours on Tuesday.
  • 8 hours on Wednesday, a holiday.
Workday counts 9 hours for Monday, 8 hours for Tuesday, and no hours for Wednesday.
Workdays (Work Hours Exceed Holiday Hours)
Work days the worker is scheduled to work, including work days that are holidays, if the scheduled hours exceed the holiday hours.
Scheduled hours for the leave date, based on the work schedule, minus any holiday hours for the same day.
Robert is scheduled to work 8 hours on Monday but has 4 hours of holiday that day. Workday counts 4 hours as leave for Monday. Workday doesn't count hours for a day that Robert books 8 hours of holiday. Even if he's scheduled to work 4 hours on that day.
Configure Days to Include
Days defined in the
Included Days
prompt. Select the
Include Holidays from the Holiday Calendar
check box to include holidays.
Scheduled hours for the leave date. Select the
Include Holidays from the Holiday Calendar
check box to include hours from holidays.
David requests leaves from Sunday through Friday, Workday counts leaves from his scheduled days; Sunday through Thursday.