Concept: Project Budgets

Concept: Project Budgets

You can gain insight into the approaching costs of a project by creating a project budget. As your projects progress, you can update them with actuals and future estimates.
You can also use project budgets to:
  • Create high-level budgets without using detailed resource forecasts.
  • Compare baseline budgets with up-to-date resource forecasts (including actuals) across your project portfolio.

Baseline Budgets

Within your organization, you can designate plans as eligible for a baseline budget using calculation types. You can also configure a business process to approve plans as the project baseline in addition to regular approval. Assign your plan as the baseline to enable reporting of baseline plans at a portfolio level.

Budget Forecasts

Once the project is under way and you have an approved budget, you can create forecasts using the same
Create Budget
button to view progress over time. To create the forecast, Workday uses revenue from the journal lines within historical periods to calculate actual hours from approved time blocks and ad hoc project time transactions. You can also include approved worker time blocks and ad hoc project time transactions in the current period. For future periods, Workday uses the resource forecast. The resulting forecast is a combination of actual amounts and budget amounts, which you can update as many times as you need.
You can create a project budget snapshot with the
Resource Forecast
report for the project. As the project progresses, you can take snapshots of the resource forecast for specific dates to estimate how the project has evolved over time. You can take 1 snapshot per month. You can't edit snapshots.
Assign your plan as a Forecast to enable reporting of forecasts at a portfolio level. Using the
Schedule Project Budget Mass Update
task, you can also regularly update draft forecast plans that use a resource forecast for the forecast calculation.

Project Financials (Plan Grid)

You can review your project financial metrics on the Plan section of the Financials tab for these Plan Categories:
  • Baseline with a status of
    Available
    .
  • Forecast.
The grid includes:
  • Inception to Date:
    The plan line amount from the project start date to the reporting period.
  • Estimate to Complete:
    The plan line amount for a period after the reporting period until the project end date.
Workday doesn't calculate these amounts for duration plans.

Project Financials (Summary Grid)

You can review your project financial metrics on the Summary section of the Financials tab. The Summary section includes these performance indicators:
Field
Description
Project Schedule
Calculates using the project start and end dates in relation to today.
Total Cost Consumed
Calculates the total consumed amount divided by the sum of total consumed and total plan remaining.
Project Spend By Type
Summarizes all project spend transactions with the project worktag, and groups the transactions by spend type.
Project Revenue For Time
Summarizes time transaction amounts from the
Contract/Billing
section for billable projects.
Project Time Blocks By Role
Pulls the approved project time blocks from the worker time submission, and then breaks them down by the project role of the worker.

Edit Plan Details

You can update a plan by selecting
Plan
Edit Plan Details
from the related actions menu:
  • Extend Plan End Date
  • Inactivate Plan
  • Rename Plan

Project Budgets Without Resource Forecasts

Without using a resource forecast, you can create:
  • Blank project budget schedules.
  • Blank project budgets without anticipated labor costs. You can then add nonlabor costs.
  • Project budgets using only labor actuals.
  • Project budgets using estimated hours by project role from the resource plan.
  • Project budgets using percent allocation by project role from the resource plan.

Project Budget Templates

You can create default configurations at the project hierarchy level using project budget templates. You can select a template when creating a project budget, saving time and preventing errors.

Consolidated Project Budgets

Consolidated project budgets deliver a virtual parent-child structure for project budgets, enabling you to link individual budgets. We also enable you to streamline activities, such as consolidating reports and adding budgetary controls.