Concept: Project Budgets
You can gain insight into the approaching costs of a project by creating a project
budget. As your projects progress, you can update them with actuals and future
estimates.
You can also use project budgets to:
- Create high-level budgets without using detailed resource forecasts.
- Compare baseline budgets with up-to-date resource forecasts (including actuals) across your project portfolio.
Baseline Budgets
Within your organization, you can designate plans as eligible for a baseline budget
using calculation types. You can also configure a business process to approve plans
as the project baseline in addition to regular approval. Assign your plan as the
baseline to enable reporting of baseline plans at a portfolio level.
Budget Forecasts
Once the project is under way and you have an approved budget, you can create
forecasts using the same
Create Budget
button to view
progress over time. To create the forecast, Workday uses revenue from the journal
lines within historical periods to calculate actual hours from approved time blocks
and ad hoc project time transactions. You can also include approved worker time
blocks and ad hoc project time transactions in the current period. For future
periods, Workday uses the resource forecast. The resulting forecast is a combination
of actual amounts and budget amounts, which you can update as many times as you
need.You can create a project budget snapshot with the
Resource
Forecast
report for the project. As the project progresses, you can
take snapshots of the resource forecast for specific dates to estimate how the
project has evolved over time. You can take 1 snapshot per month. You can't edit
snapshots.Assign your plan as a Forecast to enable reporting of forecasts at a portfolio level.
Using the
Schedule Project Budget Mass Update
task, you can
also regularly update draft forecast plans that use a resource forecast for the
forecast calculation.Project Financials (Plan Grid)
You can review your project financial metrics on the Plan section of the Financials
tab for these Plan Categories:
- Baseline with a status ofAvailable.
- Forecast.
- Inception to Date:The plan line amount from the project start date to the reporting period.
- Estimate to Complete:The plan line amount for a period after the reporting period until the project end date.
Project Financials (Summary Grid)
You can review your project financial metrics on the Summary section of the
Financials tab. The Summary section includes these performance
indicators:
Field | Description |
|---|---|
Project Schedule
| Calculates using the project start and end dates in relation to
today. |
Total Cost Consumed
| Calculates the total consumed amount divided by the sum of total
consumed and total plan remaining. |
Project Spend By Type
| Summarizes all project spend transactions with the project worktag,
and groups the transactions by spend type. |
Project Revenue For Time
| Summarizes time transaction amounts from the
Contract/Billing section for billable
projects. |
Project Time Blocks By Role
| Pulls the approved project time blocks from the worker time
submission, and then breaks them down by the project role of the
worker. |
Edit Plan Details
You can update a plan by selecting from the related actions menu:
- Extend Plan End Date
- Inactivate Plan
- Rename Plan
Project Budgets Without Resource Forecasts
Without using a resource forecast, you can create:
- Blank project budget schedules.
- Blank project budgets without anticipated labor costs. You can then add nonlabor costs.
- Project budgets using only labor actuals.
- Project budgets using estimated hours by project role from the resource plan.
- Project budgets using percent allocation by project role from the resource plan.
Project Budget Templates
You can create default configurations at the project hierarchy level using project
budget templates. You can select a template when creating a project budget, saving
time and preventing errors.