Setup Considerations: Project Plans
You can use this topic to help make decisions when planning your configuration and use of project plans. It explains:
- Why to set them up.
- How they fit into the rest of Workday.
- Downstream impacts and cross-product interactions.
- Security requirements and business process configurations.
- Questions and limitations to consider before implementation.
Refer to detailed task instructions for full configuration details.
What They Are
In Workday, you can use project plans to organize these aspects of a project:
- Project phases
- Project tasks
- Worker assignments
- Timelines
- Risks
Business Benefits
- Streamline the creation and management of your project plans.
- Reduce data entry for commonly used information.
- Increase efficiency by defining project timelines and setting milestones for billing and tracking.
- Reduce effort, maintain consistency, and avoid errors by controlling the content of project plans.
Use Cases
- Specify the window of time that workers can record their hours on a project.
- Assign workers to specific project tasks so they can log time against their task assignments.
- Add risks that might affect your project plan, such as extreme weather conditions or personnel turnover.
- Update all dates on your project tasks, task resources, or task-level resource forecasts at once.
- Export project information, such as project plan phases and scheduling information, to an XML file that can be imported into Microsoft® Project.
Questions to Consider
Questions | Considerations |
|---|---|
Do your project plans contain common information? | You can use templates to streamline data entry and reduce user errors.
When you create templates for project plans and task resources, Workday prefills the common information that most users need to enter. |
How do you want to organize the work for your project plans? | Workday organizes your project work into:
You can create project plans that have:
|
How do you want to make project tasks available for project plans? | You can restrict project tasks to specific project hierarchies, ensuring that the tasks are only available to the project plans for the projects on:
By restricting the project tasks, you ensure that project managers only see the tasks that are relevant to their project. When you don't restrict a project task to a hierarchy, it's available for use on all projects on all hierarchies. |
Do you need custom names for your project plan tasks? | You can create custom names for your project plan tasks to ensure that the names are relevant to your projects.
To create custom task names, you must first enable the security policy for the Manage: Project Custom Task Name domain. |
What date range do you want to set for workers logging their time on a project? | By default, Workday sets the date range for time entry to the start and end dates of the project.
You can configure a narrower date range for workers to log their time when you set up the tenant by using the dates specified in:
You can use multiple sources to narrow the date range. Workers can only log time where the selected date ranges overlap. |
Do you want to define the severity levels for your project risks? | You can define the severity levels of your project risks, to ensure data consistency.
Determine the security levels for your project risks before you set up your project plans. |
Recommendations
- Create templates for your standard project plans and your task resources to reduce the time users spend on data entry. Workday populates the fields on the project plan with information from its associated template.
- Restrict project plan tasks to the relevant project hierarchies for simplified task selection.
Requirements
Create a project. You can only create a project plan for an existing project.
Limitations
- Workday didn't design project plans for use with Agile methodologies.
- Project plan tasks don't have dependencies. You can't initiate a cascading update of the dates on project plan tasks.
- If a project plan has more than 500 rows of phases and tasks in theProject Plangrid, Workday has reduced performance.
- Multilevel project plans don't allow you to:
- Copy them when you create a new project by copying an existing project.
- Create project plan templates.
- Export multilevel project plans to Microsoft Project.
- TheProject Plannerreport doesn't:
- Support data sorting.
- Copy from the previous row.
- Have related actions directly from the project plan phases, tasks, or resources. To access related actions, click the hyperlink for the project plan phase or project plan task and select the menu in the preview window.
Tenant Setup
Access the
Projects
section on the Edit Tenant Setup - Financials
task to set the date range within which workers can record their hours on a project.Security
Domains | Considerations |
|---|---|
Manage: Project Integration in the Projects functional area | Enables users to export project information for use with Microsoft Project. |
Manage: Project Plan in the Project Tracking functional area | Enables users to manage and view information for both standard and multilevel project plans. |
Manage: Project Task Resources in the Projects functional area | Enables users to manage project plan tasks. |
Set Up: Project Details in the Project Tracking functional area | Enables users to manage the configuration for project details, including phases and tasks. |
Manage: Project Details in the Project Tracking functional area | Enables users to manage and view existing projects. |
Manage: Project Custom Task Name in the Project Tracking functional area | Enables users to create and edit custom task names. |
To ensure proper access, review these team member roles and activities:
Domain Security Roles | Responsibilities |
|---|---|
Project Administrator |
|
Project Manager |
|
Project Workers | Log time on their assigned project plan tasks using Time Tracking. |
Business Processes
No impact.
Reporting
Report | Description |
|---|---|
Project Planner
| Create, edit, and view a project plan on 1 page. |
View Project Plan
| Displays the project plan. |
View Project Plan Timeline
| Displays the schedule for project phases and tasks. |
You can use these report data sources to create custom reports:
- Project Time Blocks Approved Between a Date Range
- Project Plan Phases
- Project Plan Tasks
- Project Task Resources
Integrations
Web Services | Considerations |
|---|---|
Get Project Plans
Put Project Plan | Enables you to manage project plans. |
Get Project Plan without Dependencies
| Enables you to retrieve multilevel project plans without retaining the parent and child relationships between the phase levels. |
Get Project Phases
Put Project Phase | Enables you to manage project phases. |
Get Project Tasks
Put Project Task | Enables you to manage project tasks.
For Put , all task names must be unique, not just the task IDs. |
Get Project Task Resources
Put Project Task Resources | Enables you to manage project task resources. |
Connections and Touchpoints
Features | Considerations |
|---|---|
Time Tracking | You can restrict workers to log only their time during the dates on their project plan tasks, task resource assignments, or both. Workers can only log time where the selected date ranges overlap. |
Project hierarchies | You can restrict project plan tasks to specific project hierarchies. This restriction ensures that project managers only see the tasks that are relevant to their business unit, not all of the tasks in the tenant. |
Resource plans | You need to first create a resource plan for your project and assign workers to it. Then you can assign workers to the project tasks in your project plan. |
Resource forecasts | You can create resource forecasts based on your task resource assignments. |
Services CPQ | You can configure the Quote Event or Convert Opportunity Project to Project business processes to automatically create or update a project plan for quote phases and tasks after Workday creates a project from an approved and primary quote.See Services CPQ. |
Workday offers a Touchpoints Kit with resources to help you understand configuration relationships in your tenant. Learn more about the Workday Touchpoints Kit on Workday Community.