Example: Configure Employee Self-Service for Resource Forecasts
This example illustrates 1 way to configure your tenant so that workers can make updates to their hours on resource forecasts.
As a project manager, you create a resource forecast that includes Anna, a worker on multiple projects. To keep forecast hours up to date, your resource manager must perform several searches through data such as PTO, resource forecasts, and historic actuals. Managers then have to confirm the accuracy of the forecast manually.
During the project, you learn that Anna’s availability has changed unexpectedly. You want to enable workers like Anna to update their own resource forecasts directly so that you can simply review and approve changes.
- Security:Business Process AdministrationandManage: Business Process Definitionsdomains in the System functional area.
- Create a project with workers assigned to the resource plan.
- Create a resource forecast from either the project or the project plan tasks.
- From the related actions menu of theUpdate My Resource Forecast (Default Definition)business process, selectBusiness Process > Edit Definition.
- Enter the current date.
- ClickOK.
- ClickSecurity Group Restrictionsto view theInitiating Security Groups. Workday populates this field withContingent Worker As SelfandEmployee As Self.
- To include a step that enables you to review and then approve worker updates, add a row to theBusiness Process Stepstab.
- Enter these values:OrderTypeSpecifyGroupbActionReview Update My Resource ForecastProject ManagerIf you don't include an approval step, Workday auto-approves worker updates to resource forecasts.
- ClickOK.
- ClickDone.
- To review your security configurations, selectBusiness Process Policy > Editfrom the related actions menu of the business process.
- ClickOK.
When workers make changes to their resource forecasts, Workday sends requests to My Tasks for your review and approval.