Example: Set Up Award Task List
This example demonstrates how to create an award task list from an award task list template. The award task list consists of a task that occurs on a quarterly posting interval.
Your award
AWD-103: Inflation In Developing Economies
is sponsored by the Gates Foundation. As part of the award contract, your sponsor requires that the principal investigator delivers a progress report at the end of the first quarter (Q1). This report is due 10 days after Q1 ends. You want to create an award task list template consisting of this Q1 progress report, and use it to create the award task list for your award.- Create the award with an award type ofGrantand the purpose code ofSponsored Programs.
- Create the award schedule with a quarterly posting interval.
- Assign the Principal Investigator role on the award to the worker responsible for completing the progress report.
- Security: These domains in the Grants Management functional area:
- Set Up: Grants Management
- Process: Award Tasks
- Access theMaintain Award Task Typestask.
- Add a row forAward Task Type Groupand enterProgrammatic Reports InterimforName.
- To the right of the same row, add a row forAward Task Types, and enterProgress Report - InterimforName.
- ClickOK.
- ClickDone.
- Access theCreate Award Task List Templatetask.
- Select these values:FieldOptionTemplate NameGates Non-Closeout TasksRecommended for SponsorGates FoundationRecommended for Award TypeGrantRecommended for Purpose CodeSponsored ProgramsValid for Award Posting Interval GroupQuarterTask TypeProgress Report - InterimRolePrincipal InvestigatorOccurs OnEvery Award YearOn Posting IntervalsQuarter-1
- In the grid, select these values:DateTimeBefore or AfterStart or End DateRelative toDue DateNumber of Months:0Number of Days:10On or After DateEnd DatePosting IntervalStart DateNumber of Months:0Number of Days:0On or Before DateStart DatePosting IntervalEnd DateNumber of Months:0Number of Days:0On or After DateEnd DatePosting Interval
- ClickOK.
- ClickDone.
- Access theMaintain Award Taskstask.
- Select these values:FieldOptionAwardAWD-103: Inflation in Developing EconomiesTemplateGates Non-Closeout Tasks
- ClickOK.
- ClickOKandDone.
You've set up an award task list for your award that consists of a Q1 progress report. This report is due 10 days after the first quarter ends. The principal investigator can now complete the award task and attach a copy of the report to it by accessing the
Complete Award Tasks
task. You can monitor the status of the award task using the Award Task Status
report.Configure the
Award Task Event
business process to route the completed award task to the appropriate worker for review and approval.