Update the Budget Allocation on Statements of Work
Once a statement of work (SOW) is active and if the SOW Budget Allocation feature is enabled for the instance, you must use a change order to modify details. Example: the
SOW Plan Total Budget
and Charge Code Budget Allocation
can only be modified through a change order. Users see a banner on the Charge Code
tab alerting them that a charge order must be created to make any edits. - From the header, select .
- Open the appropriate SOW and select theChange Orderstab.
- ClickCreate Change Orderand enter theTitleandReason for Change Order.
- ClickNext.
- Select theCharge Codestab and make the appropriate modifications.
- ClickSave.
- When all appropriate changes have been made, clickReview and Send.If you only made changes to the charge code budget allocation, you see a message indicating the change order only requires client review.
- ClickSend to VendororRequest Approvalsdepending on what changes you made.The option forRequest Approvalsdisplays if you only made changes to the charge code budget allocation. Example: Updating amounts or moving allocated funds from one charge code to another.The option forSend to Vendordisplays if you made any changes in addition to the charge code budget allocation. Example: Updating payment types or dates.
Once the change order is approved by all required parties, the changes are reflected on the active SOW.