Steps: Mass Close Procurement Documents
Create procurement documents that are eligible for closing.
Close procurement documents when your organization no longer needs to process downstream activities, such as receipts or supplier invoices. You can close, reopen, and close again batches of completed:
- Purchase orders (POs).
- Requisitions.
- Supplier contracts.
You can filter documents with similar characteristics, such as documents in a date range, with the same worktags, or the same supplier.
When you use commitment accounting for procurement, you can liquidate the commitments and obligations associated with the documents.
- (Optional) Access theManage Exclusions from Mass Close Procurement Documentstask.Select purchase orders to manually exclude from mass closing, such as when you intend to roll the POs forward to the next fiscal period. When you set an exclusion on a PO, Workday doesn't display it for selection on theMass Close Procurement Documentstask.Security:Process: Purchase Order - Exclude from Mass Closedomain in the Procurement functional area.
- Access theMass Close Procurement Documentstask.As you complete the task, consider:
Option Description Accounting Date OverrideThe date you enter can be to a prior open period or the current one. The liquidation created as part of the close process posts using this accounting date.Close Under Tolerance %The percentage you enter remains outstanding from the requisition total quantity before it’s eligible to close.Example: You specify5%for theClose Under Tolerance %. When the requisition quantity is 100, you can close requisitions or purchase orders that received quantities of 95 or more.Close Under Tolerance AmountTolerance CurrencyThe amount that can remain outstanding from the requisition or the purchase order total before it's eligible to close.Example: You specify5,000for theClose Under Tolerance AmountandUSDfor theTolerance Currency. When the total amount is 50,000 USD, you can close documents for which you've received a total amount of 45,000 USD or more.WorktagsExample: Close documents for obsolete cost centers and projects.Inactivity DaysThe amount of days since the last activity on the procurement document.Procurement documents appear on theMass Close Procurement Documentstask when the amount of days since the last activity on the document is greater than or equal to theInactivity Daysvalue. Workday calculates the amount based on theLast Activity On or Beforefield from the procurement document.Example: You enter 30 for theInactivity Daysvalue on theMass Close Procurement Documentstask. A purchase order has theLast Activity Date On or Beforevalue of February 2, 2026.If today's date is:- March 5, 2026, the days since the last activity on the purchase order is 32 and the purchase order will appear on theMass Close Procurement Documentstask.
- February 20, 2026, the days since the last activity on the purchase order is 18. The purchase order won't appear on theMass Close Procurement Documentstask on February 2, 2026, since it hasn't been 30 or more days since the last activity.
Workday sets a document's creation date as the initialLast Activity On or Beforevalue. The value is updated when:- You make changes to the procurement document, such as updating the header or lines.
- Downstream activity occurs that originates from the document, such as creating a receipt from the originating purchase order.
Security: Configure theProcurement Document Mass Action Eventbusiness process and security policy.
Access the
Find Procurement Mass Close Requests
report to review mass close requests and access the closed business documents.Access the
Mass Reopen Procurement Documents
task when you:
- Close documents that contain errors.
- Close documents prematurely.
Reopening enables you to make your changes, corrections, or additions, and then return them to a
Closed
status.- Reopened purchase orders revert to anIssuedstatus.
- Reopened requisitions revert to anApprovedstatus.
- Reopened supplier contracts revert to aSuccessfully Completedstatus.
- You can only reopen requisitions, purchase orders, and supplier contracts closed in the current open fiscal period.
- For commitment accounting, Workday reinstates liquidated amounts that result from closing procurement documents.
Access the
Manage Exclusions from Mass Close Procurement Documents
task again to remove exclusions when POs are eligible for closing.