Concept: Step Conditions

Concept: Step Conditions

A condition is part of a business process step and consists of 1 or more rules. When the condition consists of more than 1 rule and any of them is false, the entire condition is false.
Conditions aren’t evaluated when a business process runs from a web service or EIB and is set to automatically complete.
You can optionally define entry conditions for any steps, except
Initiation
steps. For
Approval Chain
and
Consolidated Approval Chain
steps, you can also define while-running conditions and exit conditions. In addition,
Initiation
steps and
Action
steps can also include validation conditions where you set the severity of the validation to either block a step from exiting or allow a step to continue.
To add or change the condition associated with a business process step, select
Business Process
View Definition
as a related action on the business process, and then select
Business Process
Maintain Step Conditions
as a related action on the desired business process step.
You can’t take this action from the
Edit Business Process Definition
page of a business process.
For audit reporting, you can tag instances of business processes. This enables you to track and report on business process configuration changes in your tenant such as adding step conditions to a business process step. When you add a step condition to a step, an audit trail entry is created in the
Audit Trail Report
. You might see additional entries in the report for each step that you add a step condition to.
Workday prompts you to select an effective date for the step condition. The default effective date is the current date.
If you remove condition rules when there are existing initiated events, the condition rules still trigger. However, condition rules won't trigger on new events. The effective date you specify on the
Maintain Step Conditions
task is respected. Example: You remove a condition rule on an
Action
step with an effective date of 2024-01-19. Workday won't trigger the condition rule on events initiated on or after 2024-01-19 in the tenant's time zone.
You can also select a
Time Zone
for the step condition only if you enable the
Business Process Configuration Time Zone
check box on the
Edit Tenant Setup - System
task. The default time zone is the user's current time zone.
Select the
Business Process Configuration Time Zone
option on the
Edit Tenant Setup - System
task to override the default time zone on a step condition. When you enter:
  • The current date in the specified time zone, the changes take effect immediately. Users in other time zones see the changes immediately.
  • A future date in the specified time zone, the changes take effect at midnight on the specified date in the specified time zone. Users in other time zones see the changes at the corresponding date and time in their time zones.
    Example: It's 9:00 AM PST on 2024-01-22. On a business process definition, a business process administrator accesses the
    Maintain Step Conditions
    task to remove an entry condition on an
    Approval
    step. The business process administrator selects:
    • 2024-01-24 in the
      Effective Date
      field.
    • Singapore Standard Time (SST) in the
      Time Zone
      field.
    The condition rule on the
    Approval
    step won’t trigger for new events starting at midnight SST on 2024-01-24.
  • A past date in the specified time zone, the changes take effect at 11:59:59 PM on the specified date in the specified time zone. Users in other time zones see the changes at the corresponding date and time in their time zones.

Validation Conditions

Initiation
steps and
Action
steps can have a validation condition. The
Maintain Step Conditions
related action allows you to set 1 of these severities on a validation condition:
  • Warning
    : When any condition rule is true, Workday displays the error and you can still continue to move to the next business process step even if there are errors in the step.
  • Critical
    : When any condition rule is true, the step is blocked from exiting. You won't be able to continue to the next business process step until validation errors are fixed. Workday sets the validation condition to
    Critical
    by default.
When you configure a validation condition, the
Validation
column in the business process definition displays the name of the condition rule and whether it's
Critical
or a
Warning
.
When all conditions are false, the step will exit and the process will continue.
Validation conditions are only available on
Initiation
steps when the ability to revise the associated business process is built into the Workday-delivered business process or step. This ability is required to send the step back to the user's My Tasks when a validation condition is encountered.
To add a validation condition to an
Action
step, you must add the validation condition directly to the
Initiation
step of the business process definition associated with that
Action
step.
On an
Action
step, you can enable the
Enable Validation Conditions for Add Approvers
check box on the
Maintain Step Conditions
task. When you select the
Enable Validation Conditions for Add Approvers
check box on the
Action
step, and if any of the validation conditions are true, Workday triggers validation messages when a reviewer adds approvers and clicks
Approve and Send to Approvers
on the My Tasks item. When the validation condition is a:
  • Critical
    severity, Workday won't add additional approvers and the event has a status of
    Saved for Later
    . The reviewer won't be able to add approvers to the
    Action
    step until the reviewer fixes the validation errors. Once the reviewer corrects the data and clicks
    Approve and Send to Approvers
    , Workday re-evaluates the validation condition. If the validation condition is false, Workday continues to add additional approvers to the step.
  • Warning
    severity, Workday displays the warning message and the reviewer can still proceed to add approvers to the
    Action
    step. When the warning message triggers, the reviewer would need to add the approver again and click
    Approve and Send to Approvers
    . Workday then adds the additional approver to the step and the workflow continues.
When you select the
Enable Validation Conditions for Additional Approvers
check box on an
Action
step that's already in-progress, Workday won't trigger validation conditions on the step when a reviewer adds additional approvers on the step.
To determine if a business process or step can be revised, run the
Business Process Configuration Options
report:
  • If the
    Approval Options
    column includes
    Send Back
    , the business process can be revised, and you can configure a validation condition on the
    Initiation
    step.
  • If the
    Options on Save
    column in the
    Allowed Actions
    section includes
    Send Back
    , the step can be revised, and you can configure a validation condition on that step.
Roles with permission to initiate a business process that uses a defined template (such as
Change Job
) must also have View All permission on the business process security policy to ensure that Workday evaluates validation conditions.

Entry Conditions

All types of steps can have an entry condition, except
Initiation
steps. If the condition is true, the step runs. If the condition is false, the step is skipped.
Some business process definition steps have Workday-supplied entry conditions for
Action
steps, which you can’t edit. However, you can specify additional entry conditions for these steps. Both the Workday conditions and your conditions are evaluated when the business process runs. Workday skips any step that doesn’t satisfy all the entry conditions.
When a web service automates a business process, such as in an EIB spreadsheet upload, Workday automatically skips
Approval
steps, but continues to evaluate entry condition rules for
Integration
steps,
Service
steps, and
Action
steps that initiate sub-events.

While-Running Conditions

Only
Approval Chain
and
Consolidated Approval Chain
steps can have a while-running condition.
This condition works like an entry condition for each approval level in the chain. It compares the next approver to a value and if the condition is true, the step routes to that approval level. If the condition is false, it skips the current approval level and moves on to evaluate the next approval level in the chain.
When you use an
Approval Chain
or
Consolidated Approval Chain
step type for a worker with multiple managers for a single position, Workday randomly selects a person in a level and checks the while-running condition to see if that person meets the condition. If the person in the level meets the condition, the step routes to them. However, if the randomly selected person doesn't meet the condition, Workday marks everyone in that level as not required and proceeds to the next level. Before moving to the next level, Workday checks the exit condition. In scenarios where the exit condition isn't met yet, Workday continues to move up the chain. If 1 person in the previous step meets the exit condition, the approval chain exits.
Workday recommends that you don't configure a while-running condition when there are multiple managers in an approval chain.
You can use calculated fields in a while-running condition rule to determine the next approver in the approval chain when in a current step.
When you also have routing restrictions on a step, this can reduce the number of possible approvers that the while-running condition evaluates. Workday evaluates the while-running condition in each approval level first. If the while-running condition is met, we proceed to evaluate the routing restriction.
The while-running condition checks an approval level even though you might have set a routing restriction to exclude prior approvers.
Example: An
Approval Chain
step has a while-running condition to check for a manager and a routing restriction to exclude prior approvers. A manager, Betty, approves the step in a previous approval level. In a subsequent level, Betty is also an approver. The while-running condition still evaluates this approval level even though the routing restriction is to exclude prior approvers. The step goes unassigned if there isn't anyone else in the approval level to approve besides Betty.

Exit Conditions

Only
Approval Chain
and
Consolidated Approval Chain
steps can have an exit condition.
For these steps, this condition evaluates the approver who just completed this level of the chain and if the condition is true, the step exits. Like the while-running condition, an exit condition is also working while the
Approval Chain
or
Consolidated Approval Chain
is running. The difference is that when the condition is met, the exit condition exits the step; when the while-running condition isn’t met, it skips to the next level in the chain.
Starting at the second approval level, Workday evaluates the exit condition at each level including approval levels that are skipped as a result of routing restrictions and while-running conditions that might be configured on the step.
When the exit condition is never met, the
Approval Chain
or
Consolidated Approval Chain
step exits after reaching the highest approver in the management hierarchy.