Example: Single Eligibility Adjustment Within a Period
At Global Modern Services in the United States,
full-time employees have a vacation accrual of 12 hours each 2-week period. Otherwise,
they have an accrual of 6 hours each period. This example displays in-period adjustments
for Alex, who goes part-time midperiod. We compare the adjustments for the accrual with
both Start of Period or End of Period accrual frequency methods.
As the absence
administrator, you've added the Automated Accrual Adjustment service to the
Change Job
business process to enable Based-on-As-of-Date
accruals. You've also configured a semi-monthy time off plan and an accrual with
these settings:- The Accrual Period is 12/1/17 - 12/15/17.
- Semi-Monthly (Worker Based) Time Off Plan >Type:Hours
- Semi-Monthly (Worker Based) Accrual:
- CalculationTab:
- Calculation: Accrual = 12 when Time Type is Full Time, otherwise Accrual = 6
- Adjustments/Overrides Allowed: Selected
- Options:Based on As of Date
- Scheduleis blank
- Time Off Plan OverridesTab:
- Accrual Frequency Method:Start of PeriodorEnd of Period
- On 12/14, you run theChange Jobbusiness process to convert Alex from a full-time to a part-time worker.
- Workday processes the change in eligibility by:
- Adjusting the period accrual from full-time to part-time for the last 2 days in the period.
- Automatically adjusting the accrual balance at either the Start of Period or End of Period.
Activity | Accrual Frequency Method: Start of Period | Accrual Frequency Method: End of Period |
|---|---|---|
Eligibility Change 1: 12/14/17
| Full-Time to Part-Time
| Full-Time to Part Time
|
Full-Time Accrual | 10.4 hours = (12 hrs / 15 days) * 13 days | 10.4 hours = (12 hrs / 15 days) * 13 days |
Part-Time Accrual | 0.8 hours = (6 hrs /15 days) * 2 days | 0.8 hours = (6 hours / 15 days) * 2 days |
Adjusted Period Balance (Sum of 2 Accruals) | 11.2 hours = 10.4 hours + 0.8 hours | 11.2 hours = 10.4 hours + 0.8 hours |
First Line adjustment on the Automated
Adjustments tabs for Period (Adjusted Period Balance -
Original Accrual) | -0.8 hours = 11.2 hours -12 hours | 5.2 hours = 11.2 hours - 6 hours |