Example: Allocate an Amount of Time Off Units for Each New Absence Occurrence
This example illustrates how to specify a quantity-per-occurrence value on an absence table tier to allocate the same amount of time off units for each new absence occurrence.
Global Modern Services applies different waiting periods to paid sick time off plans depending on the country. Their
Spain Sick Time Off
absence table configuration includes a waiting period tier called Waiting Period Plan 10
. Workday uses a static Quantity per Occurrence
value to allocate time off units to the waiting period tier for the absence occurrences associated with the request. Each tier in the absence table includes a days-based plan. You create the time offs, time off plans, and Spain Sick Time Off
absence table:
Priority | Absence Tier Plan | Time Off Plan Balance | Time Off Plan Balance Lower Limit | Time Off Name | Maximum Unpaid Time Off Units Allowed | Days to Include | Accrual per Period |
|---|---|---|---|---|---|---|---|
1
| Waiting Period Plan 10
| 0
| 0
| Time Off J
| None
| Workdays (Non-Holiday)
| 0
|
2
| Time Off Plan 11
| 4
| 0
| Time Off K
| 0
| Workdays (Non-Holiday)
| 4
|
3
| Time Off Plan 12
| 4
| 0
| Time Off L
| None
| Workdays (Non-Holiday)
| 0
|
Create the absence table, leaving the
Quantity per Occurrence
fields empty.Set up absence occurrences.
Security:
- Set Up: Payroll (Calculations - Generic)domain in the Core Payroll functional area.
- These domains in the Time Off and Leave functional area:
- Set Up: Time Off (Calculations - Absence Specific)
- Set Up: Time Off (Calculations - Generic)
- Worker Data: Time Off (Time Off)
- Worker Data: Time Off (Time Off Manager View)
- Access theEdit Absence Tabletask and select theSpain Sick Time Offabsence table.
- In theQuantity per Occurrencecolumn for theWaiting Period Plan 10absence tier plan, enter3.
- ClickOKandDone.
You can access the
Absence Tier Time Off Entry Details
report to review how Workday splits the units by absence table tier, based on the Quantity per Occurrence
static value.Tier Allocation
Sarah requests time off for these 10 days in a single time off request:
- Wednesday - Friday (2022-09-07 to 2022-09-09).
- Monday-Friday (2022-09-12 to 2022-09-16)
- Monday-Tuesday (2022-09-19 to 2022-09-20)
Workday treats the groups of days as 1 occurrence because the
Days to Include
value is Workdays (Non-Holiday)
and Sarah doesn't select weekends.Workday allocates:
- 3 days to the first tier (Time Off J).
- 7 days to the second tier (Time Off K).