Export Project Plans for Microsoft Project
The solutions described in this section are not part of the Workday Service. See Legal Notice for details.
- Create and approve a project plan.
- Security:Manage: Project Integrationdomain in Projects functional area.
You can export a snapshot of a standard project plan for use in Microsoft Project while you continue to manage your projects in Workday.
You can only export standard project plans to Microsoft Project. You can't export multilevel project plans.
- Access the project.
- Select theProject Plantab.
- ClickExport for Microsoft Project.
- Access your Notifications, and then clickMy Reports.The exported XML file displays in a time-stamped list of files.
- Open Microsoft Project and import the XML file as a new project.Workday exports the project plan phases and the task dates to Microsoft Project:
- As is, for all the phases and the tasks, when the tasks have both start and end dates.
- As the phase and either the task start date or end date, when a task date is missing.
- As the project start date, if both the task start and end dates are missing.
In Microsoft Project, the Workday project plan phase and task fields map to these Microsoft Project fields:
Workday Field | Microsoft Project Field |
|---|---|
Phase | Task Name |
Task | Task Name (indented) |
Start Date | Start |
End Date | Finish |
% Complete | % Work Complete |
Milestone | Milestone |
Memo | Notes |