Skip to main content
Administrator Guide
Last Updated: 2023-06-23
Troubleshooting: Can't Add Resource Plan Lines to Resource Plan

Troubleshooting: Can't Add Resource Plan Lines to Resource Plan

When you access a resource plan on a project, the
Add
option is missing, and you can't add new resource plan lines.
Your project has both:
  • A resource plan inherited from a project hierarchy.
  • Task resource assignments for the inherited resource plan lines.
You can't edit inherited resource plans at the project level, only on the project hierarchy.
    Security:
    Set Up: Project Hierarchy
    domain in the Project Tracking functional area.
  1. Access the
    View Project Hierarchy
    report.
    Select the project hierarchy.
  2. From the related actions menu on the project hierarchy, select
    Project Hierarchy
    Edit Resource Plan
    .
  3. Add your changes to the resource plan lines.