Lock Leading Months Version Setting
Question
What does the Lock Leading Months
Through setting control and what does "Completion Month" mean? Also, what changes are
prevented in the locked months?Answer
- If the Lock leading Months Through field is set to blank, no months in the Version will be locked.
- If set to "Completion Month", the selected month in the "Completed Values Through" setting along with all previous months in the Version will be locked. The Completed Values Through setting can be found in the Actuals Version details.
- If set to a specific month, the system will prevent all changes to data in the Version in the selected month and any previous month. Locking months overrides all other Version access control. This means users who have access to import or have Full Access to a Version cannot change data in a locked month in that Version.
Changes that
will be
prevented in the locked
months:- Initial Balance on Standard/Cube Sheets (this doesnotinclude the "Initial Balance" columns on Modeled Sheets)
- Data imports
- Manual data entry
- Changes to Shared Formulas in the version.
- Changing the content of an Allocations rule or Eliminations rule in any way that would change the values in the locked months in the Version.
Locking
months only prevents users from making changes to
the data in those months. Attempting to view or
reference data in locked months is not affected by
their being locked. Locked months can still be used
in reports or exports with no change in
behavior.
Changes that
won't be
prevented:- The Workflow status of Levels
- Structural elements (i.e. the Organization or Account Structures)
- Values in future months even if a formula in a locked month refers to the future, unlocked month.
This feature does not include preventing changes to the
Actuals data being shown in another version or any
data in the budget version that is calculated based
on a formula that pulls from those actuals values.
If you know that going forward you will be making
changes to your actuals data and you do not want
data in other versions to change based on the
actuals then you might consider importing your
preliminary actuals values into the budget version
and then locking the months. This way you can
continue to make changes to your actuals and it
would not affect the planning version.